Construction on the 12th Avenue SE Widening Bond Project begins Monday. The project limits are 12th Avenue SE from north of Cedar Lane Road to Oak Tree Avenue. 
Traffic will be allowed at all times including access to all adjacent properties. 

The project, which is estimated to be complete in September, includes widening 12th Avenue SE from two lane to four lane, five-foot on-street bike lanes, and intersection improvements at Campus Crest and at SH-9.  Continuous sidewalks on both sides of the street with ADA ramps and stormwater improvements are also included in the project.

Traffic control devices were installed this week in preparation for construction next week. 

Questions can be directed to Tim Miles, capital projects engineer, at 366-5454.

###

ADDITIONAL INFORMATION ABOUT THE 12 AVENUE WIDENING BOND PROJECT:

Oklahoma Department of Transportation (ODOT) is administering the project.  Atkins North America, Inc. of Norman, OK is acting on ODOT’s behalf for Construction Management Services. Allen Contracting, Inc. of Oklahoma City will be the contractor.